Road Work to begin around June 9

posted on 4/24/25
posted by Road Department

Weather pending, Dustrol will begin road work beginning June 9th on various roads in Winnebago County.  The work is expected to last 4-6 weeks.  Click here to see a map.  The location and scope of each project are listed in expected order of completion:

  • R20 (Hwy 9 to MN) - Milling & Hot In-Place Recycling (Paving in mid-August)
  • Rake Area - Milling & Hot In-Place Recycling (Paving in mid-August)
  • R16 (400th St. to A42) - Hot In-Place Recycling
  • R50 (A30 to A16)- Hot In-Place Recycling
  • A30 (R50 to Hwy 69) - Hot In-Place Recycling

The work will be completed one lane at a time with a pilot car.  Sign up for updates:  https://www.iceasb.org/road-notifications/subscribe/

 

Project Contact:

Scott Meinders

Winnebago County Engineer

[email protected]

641-585-2905

More News

Road Work to begin around June 9

posted 4/24/25 · Road Department Dustrol to begin milling and hot in-place recycling work on various county roads including R20, R16, R50, A30, and local roads around Rake.

Public Health Assessment & Improvement Plan

posted 4/23/25

Winnebago County Approves 2026-2030 Five Year Construction Program

posted 4/16/25 · Road Department Five Year Construction Program to include 12 bridge replacements and 17.5 miles of resurfacing.

Winnebago County Campgrounds to Open for the Season

posted 4/11/25 · Conservation

Lake Catherine Cabin to Reopen

posted 4/11/25 · Conservation